INFORMATION
on support for investment projects on the "single window" principle within the territory of the urban district of the municipal formation
City of Irkutsk
To reduce administrative barriers in the implementation of investment projects within the city of Irkutsk, a Regulation for the support of investment projects based on the "single window" principle has been developed and approved by the city administration of Irkutsk. It was adopted by the decision of the Irkutsk city administration № 031-06-653/21 dated September 13, 2021.
Subject of regulation of the Regulation
The Regulation defines the procedure for interaction between the administration bodies of Irkutsk City (structural subdivisions of the city administration) and potential investors based on the "single window" principle.
Support forms during the support of investment projects
-
Providing informational and advisory support to the Investor.
-
Providing organizational support to the Investor.
The body of the Irkutsk city administration that provides informational, consulting, and organizational support to the investor is the Committee on Economy and Strategic Planning of the Irkutsk City Administration (hereinafter – the Coordinator).
How the Investor can contact the Irkutsk city administration:
-
Orally: consultation on possible support measures, assistance in preparing a written request for project support (if necessary).
-
In writing: submitting a request along with a Project Resume in the formats provided by the Regulation.
To whom should the Investor address:
- To the Mayor of Irkutsk, the Vice-Mayor of Irkutsk (the investment authorized person in the city of Irkutsk), the city administration bodies, or the Coordinator.
Procedure for the Investor’s inclusion in support
-
Submission of a written request by the Investor for support of an investment project.
-
Consideration of the Investor’s request by the Coordinator (within 3 working days).
-
If the documents meet the requirements, the Coordinator prepares a conclusion regarding the expediency (or non-expediency) of supporting the project (within 15 calendar days). The project is considered expedient for support if all criteria are simultaneously met.
-
Sending the conclusion on the expediency (or non-expediency) of supporting the project to the investment authorized person in Irkutsk for decision-making (within 5 working days).
-
After deciding on the expediency of supporting the investment project, the Coordinator prepares an order for supporting the investment project (within 10 working days).
In case of non-expediency, a corresponding response is prepared for the Investor within 10 working days.
Support for the investment project begins from the date of signing the Order.
Termination of support:
Support for the investment project is terminated in the following cases:
-
Completion of all activities outlined in the Action Plan;
-
The Investor’s refusal to support the investment project through a written withdrawal request prepared in accordance with Appendix 3 of the Regulation;
-
Failure by the Investor to fulfill deadlines for individual activities listed in the Action Plan, for which they are responsible, for more than ninety working days;
-
Liquidation or bankruptcy of the Investor, or termination (restriction) of their activities by court decision;
-
Evasion by the Investor from providing information upon request of the Coordinator and/or responsible project performers more than once;
-
Presence of warnings (instructions) from regulatory (supervisory) authorities regarding violations of applicable Federal legislation in relation to the Investor, concerning activities within the investment project being supported.
Regulation on the Support of Investment Projects under the One-Stop Principle